COD IN THE IS-31 PLANT, NORTH CAROLINA (USA)

Press GRS

Business Layout Pack

On the 30th, we obtained the COD (Commercial Operation Date) at the IS-31 plant in Bladenboro, North Carolina (USA).

In order to do this, all the inverters of the plant had to be started up and they had to reach 20% of the nominal power of the plant.
As relevant data say:

  • It is the largest solar plant that GRS has built to date, without partners. The plant has 43.12 MWdc and has 127,560 modules, 35 inverters of 1 MW and single-axis tracker.
  • More tan 1600 Monoline trackers have been installed.
  • The construction began on october 2016.
  • An average of 90 electricians have been working every day duing the last three weeks to achieve the boundary post.
  • 13 people from Spain have moved to the plant to help with the start-up and the commissioning in the last two weeks.
  • During the next 3 weeks, all trackers will be set up and the pre-delivery tests will be completed.
Substation

Photo of the substation on the same day of the connection

Press GRS

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.